Tacoa
DCS |
|
Construction
Period: 2004-2005. |
|
Project
Name: Tacoa Power Plant, Units 7, 8 & 9
- DCS (Distributed Digital Controls) Project. |
|
Owner: La Electricidad de Caracas (EDC). |
|
Purchaser: Toshiba Corporation (Mitsui & Co. Ltd). |
|
Site: Caracas, D.F. |
|
Scope of Work:
- Installation and electrical works.
- Supply of cables & materials. |
|
|
|
|
|
|
|
For larger views, click on the images. |
|
|
|
 |
CADAFE
Thermal Plant |
|
Construction
Period: 1978–
1984. |
|
Project
Name: PLANTA
CENTRO THERMAL POWER STATION, Units 3, 4 and 5. |
|
Owner: COMPAÑÍA ANONIMA DE ADMINISTRACION
Y FOMENTO (CADAFE) |
|
Units 3
& 4: Installation of Two 1400 Ton/Hour
Boilers and Associated equipment for 400 MW
generating Units No 3 & 4, AFE including
erection of Steel Structures of the Boilers. |
|
Unit
5: Installation of 1,400 Ton/Hour
boiler for 400 MW generation unit. |
|
|
|
|